Workstream Delivery Status
WS1
Security Hardening + Phase Zero
WordPress security, Phase Zero design comps
| Deliverable | SOW Commitment | Deadline | Status |
|---|---|---|---|
| Security Hardening | WordPress security audit, plugin hardening, user access controls, uptime monitoring configured | Apr 10 ✓ | Delivered |
| Phase Zero Design Comps | Homepage wireframe + 2 interior page comps, mobile + desktop; brand-aligned with Sperry identity | Jun 1 — 27 days | Not Started |
Action Required: Phase Zero design has not started. Jun 1 deadline is 27 days out — needs to begin this week to allow time for Sperry review and revisions. Assign design sprint immediately.
WS2
Email Campaign
11-email calendar • Res/Comm segmentation • Apr 1–Jun 30
| SOW Description | Scheduled / Sent | Status | |
|---|---|---|---|
| Email 1 | Segment kickoff — Residential vs. Commercial list split | Sent Apr 1 ✓ | Sent |
| Email 2 | Spring pruning — seasonal urgency, residential | Sent Apr ✓ | Sent |
| Email 3 | Storm prep / risk assessment — commercial track | Sent Apr ✓ | Sent |
| Email 4A & 4B | Deep-care services — Res (4A) + Comm (4B) variants | Sent May ✓ | Sent |
| Email 5 | Mid-season check-in / estimate offer | May 6 — Tomorrow | Scheduled |
| Emails 6–11 | Remaining calendar through Jun 30 — segmented sends | May–Jun 30 | Drafted & Queued |
Notes: 5 of 11 sends complete. Email 5 scheduled for May 6 6am PDT. Emails 6–11 drafted and queued in Kit through Jun 30. Res/Comm segmentation active — all sends branch by list. Kit V4 API tooling operational; send_at preservation issue resolved.
WS3
Meta Advertising
Paid social — campaign build, creative, execution through Jun 30
| Deliverable | SOW Commitment | Deadline | Status |
|---|---|---|---|
| Campaign Architecture | Campaign, ad set, and ad structure built in Meta Ads Manager; targeting configured for Lane + Benton County | Apr 14 ✓ | Built |
| Creative Assets | Ad creative produced and uploaded; copy variants ready for A/B | Apr 14 ✓ | Ready |
| Campaign Live | Campaign active and spending; performance monitoring in place through Jun 30 | Apr 14 — 21 days ago | Paused — Pending Approval |
Blocked: Campaign built and ready. Paused pending Rob and Michele's approval of creative. 21 days of ad spend opportunity have elapsed since the Apr 14 go-live target. Need go/no-go from client this week to salvage remaining Q2 window (56 days, ~$7,500 budget).
WS4
Automation — Lead Warming + Club Welcome
7 automated emails across 2 sequences; Zapier triggers
| Sequence | SOW Commitment | Deadline | Status |
|---|---|---|---|
| Lead Warming 3 emails |
Automated 3-email nurture triggered when new Jobber estimate is created; warms lead toward booked job via Zapier → Kit sequence | Apr 27 — 8 days overdue |
Not Live
Designed, content drafted; not in Kit/Zapier
|
| Club Welcome 4 emails |
Automated 4-email welcome sequence for new Plant Health Care club members; triggered on Jobber job completion or tag event | Apr 27 — 8 days overdue |
Not Live
Designed, content drafted; not in Kit/Zapier
|
| Zapier Triggers | Jobber → Kit webhook connections for both sequences; tested and live | Apr 27 — 8 days overdue |
Not Configured
Webhook helpers built; not deployed to production
|
Priority Action: WS4 is 8 days overdue. All sequence content is drafted and webhook tooling is built (kit_ui_inject.js, wp/webhooks_add_form.js). Blocker is final Zapier configuration and Kit sequence creation in production. Estimated to complete: 4–6 hours of implementation. Schedule this sprint immediately.
Payment Schedule
| Payment | Due Date | Amount | Status |
|---|---|---|---|
| Signing payment | Mar 26, 2026 | $4,500.00 | Collected |
| Monthly — April | Apr 1, 2026 | $2,083.33 | Collected |
| Monthly — May | May 1, 2026 | $2,083.33 | Collected |
| Monthly — June | Jun 1, 2026 | $2,083.33 | Upcoming |
| Monthly — July | Jul 1, 2026 | $2,083.33 | Upcoming |
| Monthly — August | Aug 1, 2026 | $2,083.33 | Upcoming |
| Final payment | Sep 1, 2026 | $2,083.35 | Upcoming |
| Totals | $17,000.00 | $8,666.66 collected • $8,333.34 remaining | |
Open Action Items
-
1WS4 Automation — Go LiveOverdue 8d
Lead Warming (3 emails) + Club Welcome (4 emails) sequences not in Kit. Zapier triggers not configured. Content and tooling are ready — needs a 4–6 hour implementation sprint.Owner: BOSSTORQUE • Priority: Critical • Was due Apr 27 -
2Meta Campaign — Client ApprovalBlocked
Campaign fully built and paused. Rob and Michele have not approved creative. 21 days of ad opportunity have elapsed. Client decision needed this week.Owner: Rob Miron / Michele Hatfield (Sperry) • Priority: High • Was live Apr 14 -
3WS1 Phase Zero — Design Sprint Start27 Days
Homepage wireframe + 2 interior comps not started. Due Jun 1 (27 days). Must begin this week to allow client review and revision cycles before deadline.Owner: BOSSTORQUE • Priority: High • Due Jun 1